November 2008
Addition of perimeter building foundations
for the south UC expansion. |
 |
November 2008
Interior foundation column pads for south UC
expansion. |
|
November 2008
South firewall complete and braced. |
 |
November 2008
Installation of concrete foundation walls for
the north UC expansion. |
 |
November 2008
Completion of elevator in north UC expansion. |
 |
December 2008
Footings and foundations complete. |
 |
December 2008
Reception of structural steel |
 |
December 2008
Build up of building pads and prepare for
pouring of building slabs. |
 |
December 2008
Pouring of building slabs. |
|
December 2008
Complete utility tunnel walls and
foundations. |
 |
December 2008
Installation of under slab utilities. |
 |
January 2009
All foundations, foundation walls and grade
beams are complete. |
 |
January-February 2009
South-Under slab sanitary storm piping to be completed. |
 |
January-February 2009
South-Under slab electrical conduit to be completed. |
 |
January-February 2009
South-Structural steel erection and second floor/roof
decking to begin and be completed. |
 |
March 2009
South-Light Guage Metal Framing,
South Roofing, Sheathing and Masonry to begin.
South Structural steel to be erected. |
|
March 2009
North-under slab utilities to be completed.
Selective demolition and framing of curtain wall,
structural steel to be erected.
|
|
April 2009
South roofing to be completed, exterior walls
going up and masonry complete on east end. |
 |
April 2009
North-Tie in to existing building structure.
Curtain walls to go up. |
 |
| |
|
| |
|
| |
|
| |
|
| |
|